We also discuss the risk management process to ensure that risks are identified,prioritized and tracked throughout the life of the project.. Issue in Project Management...6 Difference be
Trang 1MINISTRY OF EDUCATION AND TRAINING
UNIVERSITY OF ECONOMICS AND FINANCE
Trang 2We also discuss the risk management process to ensure that risks are identified,prioritized and tracked throughout the life of the project At the same time, wealso present some examples of how risk management can help achieve projectgoals, enhance reputation, and save costs.
Finally, the report presents a Case Study and applies the above techniques in it
to easily understand the sequence of steps in risk management planning as well
as offer some prevention and mitigation measures risk for the project
Trang 3ACKNOWLEDGEMENT
We would like to express our gratitude to the Faculty of InformationTechnology, University of Economics and Finance, Ho Chi Minh City forcreating favorable conditions for me to complete this project We would like toexpress our deep gratitude to Mr Tran Thanh Cong, subject lecturer Heenthusiastically supported us to complete this final project and guided usthroughout the course We would like to express our sincere thanks to theteachers of IT Faculty - University of Economics and Finance, Ho Chi MinhCity for teaching and equipping us with valuable knowledge about the subjectE-Commerce Project Management Sincere thanks to family, brothers andsisters, friends who have supported and encouraged us during our study andresearch Through the E-Commerce Project Management course, we havelearned a lot of skills such as teamwork, assessing project risks and coming upwith the best solution We tried very hard to complete the project completely,but due to our limited knowledge and limited experience, we inevitably mademistakes We look forward to receiving the sympathy, comments of teachers,and suggestions from friends so that we can improve more and more
Thank you very much!
Trang 4TABLE OF CONTENTS
ABSTRACT
ACKNOWLEDGEMENT
TABLE OF CONTENTS
TABLE OF CONTENTS OF FIGURE & TABLES
CHAPTER I: THEORETICAL BASIS
Learning Objectives 6
Definition of Project Risk Management 6
Risk vs Issue in Project Management 6
Difference between “Issues & Risks” 7
The driver of Risk Management Plan 7
The importance of risk management in business 7
CHAPTER II: TYPES OF PROJECT RISK MANAGEMENT
Financial risk management 8
External risk management 9
Performance risk management 9
Schedule risk managementent 10
Operational risk management 11
CHAPTER III: EXAMPLE OF PROJECT RISK MANAGEMENT
Difference between Positive and Negative risk
Trang 5Example of Positive and Negative risk
CHAPTER IV: PROJECT RISK MANAGEMENT PLANNING & CASE STUDY
Project Risk Management planning
Case study
Identify possible risk events 15
Prepare risk analysis and contingency plans 16
Prioritize the risk 16
Assign a risk owner 19
Monitor risks & communicate project tracking 20
Respond to risk events 21
Assess your risk management plan 21
CHAPTER V: CONCLUSION
References
TABLE OF CONTENTS OF FIGURE Figure 1 Financial risk 9
Figure 2 Schedule risk management 10
Figure 3 Operational risk management 11
Figure 4 Project building process 15
Figure 5 Buble chart 19
Table 1 Example of Positive and Negative risk 13
Table 2 Definitions of risk probability and impacts 17
Table 3 Probability and impact matrix 18
Trang 6CHAPTER I:
THEORETICAL BASIS
I Learning Objectives
Understand the concept of risk, risk types, and risk classification
Master the skills of analyzing and assessing the risks that may occur in theorganization
Know how to plan for risk management and mitigation, includingeffective risk reduction and prevention methods
Understand the factors affecting risk management and know how tooptimize the risk management system in the organization
Capable of assessing and proposing solutions to deal with existing risks,ensuring the safety and stability of the organization's business activities
II Definition of project risk management
Project risk management is the process of identifying, anticipating, mitigating,preventing, and responding to potential risk events that may occur during aproject Project risk refers to anything in the project that doesn’t go as planned.One key thing to note about project risk management is that it’s not all aboutprevention Instead, it’s about acknowledging that things don’t always go asplanned and preparing risk mitigation strategies
III Risk vs issues in project management
Trang 7 Risk:
A risk is an event that may occur that could affect a project A risk can be
a benefit or a challenge That could happen in the future
Issue:
An issue in business is a challenging event that has already occurred or iscurrently occurring Even with careful planning, challenges can arise, andproject managers can use problem-solving skills to create positivesolutions
IV Difference between “Issues” & Risks”
Present focused
Always negative
Documented in “Issue register”
Response will be “Issue
work-around”
Future focused
Can be postive or negative
Documented in “Risk register”
Response will be done based on
“risk response planning”
V Drivers of The Risk Management Plan
The main drivers of a risk management plan are given here:
Early identification of risk and defining its mitigation plan reduces thenegative impact of the risk on the overall project
One of the main drivers of risk management plan is to reduce thedeviation of planned effort, cost, and schedule The risk managementplan also ensures that specified functionalities are properlyimplemented
VI The importance of risk management in busines
Maintain the stability of business operations
Trang 8 Ensure the safety and security of working for the organization
Protect your business from damage to property, resources and people
Cut down on remedial costs incurred due to risks
Creating conditions for businesses to develop and compete sustainably
There are several ways to approach risk management depending on the lens thatyou look through Here are the most common approaches to managing varioustypes of business risk
1 Financial risk management
Financial risk management is the practice of protecting economic value in
a company by managing financial risks - primarily operational risk,applied signal risk and market risk, underfunding, not enough capital,
For risk management in general, financial risk management entailsidentifying the source, measuring the risks, and planning to address them
Financial risk management focuses more on when and how to hedge risk,often using financial instruments to manage risk costly risks
Example: Lack of capital - The cost of planning large strategic projects,
need to mobilize investment capital for the plan
Trang 9Figure 1 Financial risk
2 External risk management
The type of external risk management is the process of identifying,assessing, planning, and managing risks related to external factorsaffecting an organization's operations Examples include governmentpolicy changes, market fluctuations, the impact of natural disasters orcybersecurity threats, new regulations, emergencies, weather events,supply chain issues and market events
External risk management enables an organization to respond and copewith unforeseen changes and minimize their impact on the organization'sbusiness The strength of external risk management is that it helpsorganizations respond quickly and effectively to uncertain or changingexternal conditions without affecting the organization's profitability orencountering other problems consequential difficulties such as loss ofproperty or damage to the reputation of the organization
Example: Change in staffing: The project has difficulty recruiting and
retaining staff or project managers, causing the project to be delayed
3 Performance risk management
Performance risk management is the process of managing risks related to
an organization's performance in decision making and business strategyimplementation This type of risk management focuses on optimizing the
Trang 10 Example: Lack of information and thorough analysis on factors affecting
the project such as market, customers, competition, and funding
4 Schedule risk management
Schedule risk is the risk that activities take longer than expected and isoften the result of poor planning It is closely related to cost risk, asschedule delays often increase costs and also delay project outcomes,including benefits
Delays lead to missed planning milestones and possible loss ofcompetitive advantage Schedule risk leads to cost risk because longerprojects cost more It can also lead to performance risks, due to misseddeadlines for completing the intended task
Example: Delayed schedule - When the project has a high degree of
complexity, there is a greater chance of items being missed during scopedevelopment This oversight can cause many changes to occur duringproject execution
Figure 2 Schedule risk management
Trang 115 Operational risk management
Operational risk management is the risk of loss due to inefficient or faultyinternal processes, people, systems, or external events that could disruptthe flow of business operations Losses can be direct or indirectfinancially
Example: A poorly trained employee could lose a sales opportunity, or
indirectly the company's reputation could suffer due to poor customerservice
Figure 3 Operational risk management
Trang 12CHAPTER III:
EXAMPLES OF PROJECT RISK MANAGEMENT
People tend to associate the word “risk” with a negative impact But in projectrisk management, the term applies to anything that doesn’t go as planned Inother words, it also includes events that can positively affect your project
1 Difference between Positive and Negative risk:
An opportunity to improve your
project A threat to your project's success
Often gives improved results Results in a negative outcome or
even failure for your project
Should be seized and built upon Should be avoided, minimized,
or eliminated
Managing positive risks can
include exploiting, sharing, and
enhancing the risk
Managing negative risks caninclude avoiding, transferring, ormitigating the risk
Table 1.1 Difference between Positive and Negative risk
Trang 132 Example of Positive and Negative risk:
Table 1 Example of Positive and Negative risk
Positive risk refers to unplanned events
that benefit ofproject
Negative risk means that the unplanned event has a detrimental effect on project
Miscalculation of a project budget could
lead to cost savings or funding additional
projects
Supplier loss
Example: If a company completes a
project under budget, it might be because
of the project manager's miscalculation of
the costs or lack of prudence While
miscalculating a project's costs is a risk,
the result in this example is positive,
resulting in the company being able to
reallocate its profits into activities that
support its growth and development
Example: You could
go past your deadline, surpass your budget, orhave a supplier shut down in the middle of the project
Trang 14CHAPTER IV:
PROJECT RISK MANAGEMENT
PLANNING & CASE STUDY
I Project risk management process: 7 steps
Identify positive risk events
Risk identification
Prioritize risk
Assign a risk owner
Monitor risk and communicate project tracking
Respond to risk events
Assess your risk management plan
II Case study:
“FIT ME BEST” APPLICATION ANNOUNCEMENT PROJECT
Slogan: Be yourself in the most perfect version.
You are a project manager for Fashion Brand Zara The brand is working on anew project on the occasion of the upcoming April 30 holiday Due to fundingfrom stakeholders who are investors, the project is underway and will hit themarket in the near future
You have been asked to lead the project to manage, control and plan thisproject
The goal of the project is to sell as many items as possible, gain a 30% increase
in new customers and build brand trust
Trang 15Based on the concept that was developed, the project team developed a schedule
of the project's progress from concept to project completion
And to control well and ensure that the project goes smoothly, it is indispensablefor the risk management process, that is, the activity of anticipating potentialrisks and planning to respond to it
Figure 4 Project building process
1 Identify positive risk events:
The first step in the planning process is to identify possible risk events beforethe project starts This is sometimes referred to as conducting a
“premortem.”
Trang 16 Cost less than expected
Early project completion time
Need less than of the original plan
2 Risk identification
After the brainstorming session, it’s time for risk assessment Determinethe likelihood of each risk event happening, the estimated impact size, and
a potential response plan
Information from past projects can help your team predict risk probabilityand impact
Plan progress has been delayed
Cost is higher than expected
Change steps from plan
Investors withdraw capital
The party involved did not complete the project on time
Project security leaked to competitors
HR quits
Specialized personnel are not skilled enough
Project manager mispredicted completion time
Data system infected with virus
Trang 17 This helps you set priorities while looking at the big picture This way,you can understand which risks deserve more attention and which you canreasonably tolerate
Plan progress has been delayed
Cost is higher than expected
Project security leaked to competitors
Specialized personnel are not skilled enough
Data system infected with virus
Table 2 Definitions of risk probability and impacts
Definitions of risk probability and impacts: When there is a probability
assessment of a particular risk is 70% in qualitative analysis A risk-averseperson might think 70% is very high, while a risk-averse person might think70% is a low number The definitions of likelihood and impact help standardizethese interpretations, help everyone understand the extent of a risk, and also helpcompare risks across projects
Trang 18Table 3 Probability and impact matrix
Probability and impact matrix: A grid showing the association between the
likelihood of a risk occurring and its impact on the project's objectives if the riskoccurs Descriptive terms (such as very high, high, medium, low and very low)
or numerical values may be used for likelihood and impact When numericalvalues are used, these values can be multiplied together (Probability x Impact, P
x I) to give a probability and impact score for each risk (risk score), allowing thelevel of risk to be assessed relative priority of individual risks This matrix will
be used together with risk appetite, for example, we will divide those risks with
a risk score higher than 0.24, then classify those risks into a group, need to havesolutions for those risks This is to bring it to the lower risk score zone From0.07 or less, put in a group without giving immediate response plan, just put on
a list to watch later (watchlist) The risk appetite of different projects, they willchoose different risk score thresholds to arrange